Cold-Formed Steel Roof Truss Engineering: A 34'-7" Clear Span With No Internal Supports
The architect wants an open, column-free interior. The client wants a tray ceiling with clean sightlines. And the roof spans more than 34 feet, well beyond what a standard truss layout can carry without a support column landing exactly where nobody wants one.
That was the brief on a recent project: a 4,110 sq ft single-storey home with a hip roof, a 34'-7" clear span, a tray ceiling, and no internal supports allowed. Here is how we engineered it, and what it means for contractors and developers facing long spans on their next job.
The project at a glance
- Building: single-storey custom residence, 4,110 sq ft
- Roof: hip roof with tray ceiling
- Clear span: 34'-7" with zero internal supports
- Framing: cold-formed steel (CFS) roof trusses using 3" hat channel
- Scope: structural engineering, 3D BIM modeling, truss detailing, permit set and CNC production files
Why cold-formed steel was the right call
Wood trusses start to struggle, structurally and economically, once spans pass about 30 feet without intermediate bearing. Deeper wood members add weight, cost and lead time, and still may not match the strength-to-weight ratio of cold-formed steel.
For this build, our engineering team designed a single-span CFS truss system that carries the full 34'-7" without a single interior column. The result is a fully open floor plan, a tray ceiling that reads clean and uninterrupted, and a roof structure engineered for real-world wind and seismic loads, not just for the drawings.
It's a clear example of why light gauge steel framing (LGSF) keeps gaining ground on wood for custom residential work in the US.
Key engineering features
Clear span with zero internal supports. The truss system was engineered end to end for the full 34'-7" width, removing the mid-span column that would have broken up the open plan.
3" hat channel construction. The profile was chosen for its strength-to-weight performance across a long single span, which matters as much for material use and shipping weight as for structural capacity.
Hip roof geometry, fully coordinated in 3D. Hip roofs are harder to truss than gables because every truss changes length and geometry as it steps down toward the eaves. Full 3D BIM coordination meant every truss in the sequence was engineered and detailed to fit, with no field-fit surprises.
Tray ceiling built into the engineering. A tray ceiling adds real complexity: the trusses must form the raised ceiling profile without compromising the load path. We designed for it from the first calculation instead of adapting the trusses afterward.
Full scope: from engineering to CNC-ready files
A common question from GCs and developers is what "CFS truss engineering" actually includes. On this project, our scope covered the whole path from concept to fabrication:
- Structural engineering with load calculations, gravity and lateral analysis, and wind and seismic design for the local code jurisdiction (engineering services)
- 3D BIM modeling of the complete truss system, including the hip roof geometry (modeling and detailing)
- Steel truss detailing at shop-drawing level for every member, connection and hat channel component
- Permit set prepared for submission to the local building department (permit sets)
- CNC production files that feed directly into roll-forming equipment, cutting manual layout time and fabrication errors
This matters because handoffs are where projects slow down. When engineering, modeling and permit drawings come from one coordinated source, there is no mismatch between what the engineer calculated and what gets fabricated and installed.
What this means for your next long-span project
If you're a general contractor, developer or steel framing business bidding a job with a long clear-span roof, three lessons from this project apply directly:
- Long spans don't have to mean interior columns. With the right custom truss engineering, clear spans well over 30 feet are achievable without compromising the architect's design.
- Permit documentation shouldn't be a separate phase. Engineering, BIM modeling, truss detailing and permit sets should come from one coordinated workflow, not separate vendors working from different drawing versions.
- CNC-ready output shortens the path to fabrication. Production files generated from the engineered model leave less room for errors between design intent and what gets cut and assembled.
We've solved other non-standard LGSF problems the same way, including a custom 30-foot climbing wall for a commercial building. For more on where LGSF projects usually go wrong, read the hidden engineering challenges behind LGSF buildings.
Frequently asked questions
How long can a cold-formed steel roof truss span? It depends on the truss profile, loads, spacing, roof geometry and local code. On this project, an engineered CFS truss system cleared 34'-7" with no interior supports. Every span must be confirmed by project-specific engineering.
Are steel roof trusses more expensive than wood? Material cost per truss can be higher, but on long spans steel often removes beams, posts and interior footings, and CNC fabrication cuts labor and waste. Compare the total installed cost, not just the truss price.
Can CFS trusses handle a tray or vaulted ceiling? Yes. Tray and vaulted ceilings are designed into the truss geometry from the start, as on this project.
What do you need to quote a CFS truss project? Architectural plans, roof plan and sections, design loads or location for wind and seismic criteria, and your preferred software or roll-forming machine if you need production files.
Planning a long-span roof?
If you have a project with a challenging clear-span requirement, send us the drawings. We'll review the span, confirm what's achievable and outline the engineering, detailing and production scope.
Book a 15-minute project call, email marketing@ubcbim.com, or browse our residential projects.